Free sample · PMP questions

15 questions from the PMP question bank

PMI-style PMP 2026 exam questions, with an instant explanation for every answer showing what is right and wrong.

Question 1 of 15
Move freely between questions — no need to answer first
0/15

This is just a small sample

The full bank holds over 2300 questions in all patterns, with diagnostics that pinpoint your weak point at every enabler. Subscribe and start your real preparation.

Subscribe to the full platform

Not ready to subscribe? Get more for free:

✈️ Telegram bot — 2 questions daily (60 free)
Sample report

This is what you get: enabler-level diagnostics

An illustrative example of the exam-simulation report. The results and figures here are representative only — your report is built on your actual performance.

⚠️ This is a sample only — the numbers and results here are illustrative and unrelated to your performance on the demo questions.
ExamAce SAMPLE Diagnostic report
Exam simulation · 180 questions · 240 minutes
Other platforms say
"You’re weak in the Process domain." — a broad domain with ten tasks and 64 enablers. Where do you start?
ExamAce says
You’re weak specifically in enabler 2.6.2, out of 138 enablers — and we give you its topics to review.
68%
Your estimated readiness
Close · needs focused strengthening
People weight 33% 78%
Process weight 41% 58%
Business Environment weight 26% 70%
Weakest enablers — where you lose points

Enablers below 70%, ordered from weakest, with each enabler’s topics to review directly (per the PMBOK Guide).

Enabler Task Domain Your score Topics to review
2.6.2Quantify risks and allocate contingent financial resources Plan and manage finance Process 33% Contingency reserve · Expected Monetary Value · quantitative risk analysis
3.5.2Analyze risks Plan and manage risk Business Environment 40% Probability–impact matrix · qualitative analysis · quantitative analysis
2.8.5Create the project schedule Plan and manage schedule Process 50% Critical path · total and free float · network diagram
2.5.7Define a negotiation strategy Plan and manage procurement Process 50% ZOPA · reservation price · negotiation strategy
1.2.3Implement an agreed-upon resolution strategy Manage conflicts People 60% The five conflict-resolution styles · collaborate vs. compromise · appropriate escalation
Your strongest enablers

Maintain your level with light review.

1.1.2 Promote the shared vision · 92% 2.2.3 Decompose the scope · 88% 3.3.1 Execute the change control process · 85%
Suggested review plan

We ordered it from the weakest by impact — start at the top.

1Start with 2.6.2 Allocate the financial reserve (weakest enabler): review the contingency reserve and the Expected Monetary Value calculation, then practice its questions in the Review Center.
2Then 3.5.2 Analyze risks: practice building the probability–impact matrix and ranking risks by the product.
3Then 2.8.5 Create the schedule: review the critical path and float from the network diagram.
The report is built on your performance in the exam simulation and the Review Center, covers 138 enablers across the three domains, and is exported as a branded PDF.
Get your full report