Stakeholders, Communication & Conflict: Engage by Position, Manage Not Avoid

Not all stakeholders are managed the same way.

Updated 2026·9 min read
  • High power, high interest — Manage closely
  • High power, low interest — Keep satisfied
  • Low power, high interest — Keep informed
  • Low power, low interest — Monitor

Identify stakeholders and classify them by power and interest to choose the right engagement style; high power and high interest are managed closely. Plan communication: what, to whom, when, and through which channel. In conflict, collaborating and problem-solving is usually best, compromise is a quick middle ground, and forcing is the last resort. Conflict managed openly improves decisions.

Common mistake

Trying to please all stakeholders equally. Instead, differentiate engagement effort by their power and interest.

Engage stakeholders by their position, and manage conflict rather than avoid it.

Ready to start serious PMP prep?

Subscribe now
Read the details

Stakeholder engagement begins with identification and analysis, then classification using models such as the power-interest matrix to set the right engagement dose per group. On top of that sits communication planning: defining the message, audience, timing, channel, and feedback mechanism. When conflict arises, choosing the right style, collaborating and problem-solving for a durable solution and compromise for speed, turns disagreement into a better decision rather than avoiding or forcing it. The analysis is complemented by the stakeholder engagement assessment matrix, which compares each stakeholder's current engagement level with the desired one across five levels: unaware, resistant, neutral, supportive, and leading, to focus effort on closing the gap.

What surprises project managers most is not an expected objection from a known party but a late one from a quarter nobody counted. The usual cause is that stakeholder identification happened once at the start and the file was closed. The Eighth Edition addresses this outright: identification, prioritization, and engagement should be reviewed and updated routinely, or at least when the project progresses through phases. Stakeholders are not a list but a shifting field.

Definition and Foundation

The Stakeholders performance domain addresses processes and tools related to stakeholder engagement, from identification through monitoring their engagement during the whole life cycle of the project. The sponsor, team members, and all the people impacted by — or who feel they may be impacted by — the project count as stakeholders. Four points set the frame:

  • Range — a project can have a small group of stakeholders or potentially millions; there may be different stakeholders in different phases, and the influence, power, or interests of stakeholders may change as the project unfolds.
  • Inclusion — effective identification, analysis, and engagement covers those internal and external, those supportive, those neutral, and opponents who are not supportive of the project.
  • Cadence — identification, prioritization, and engagement are reviewed and updated routinely or at phase transitions.
  • Weight — technical project management skills matter, but the interpersonal and leadership skills to work with stakeholders are just as important, if not more so.

The guide links this domain closely to communications management, and names negotiation and conflict management among the key skills to develop in it. Its processes are seven: Identify Stakeholders, Plan Stakeholder Engagement, Plan Communications Management, Manage Stakeholder Engagement, Manage Communications, Monitor Stakeholder Engagement, and Monitor Communications.

Among its key concepts is stakeholder satisfaction: it should be prioritized and integrated into the project objectives, and the key to driving it is maintaining a focus on continuous communication with all stakeholders — customers, end users, managers, executives, and team members — to understand their needs and expectations, address issues as they occur, and manage conflicting interests. It adds team engagement: project team members are also critical stakeholders and should be treated as such.

How It Works in Practice

Stakeholder mapping and representation

A method of categorizing stakeholders, which assists the team in building relationships with them. Common methods include the power/interest grid, power/influence grid, or impact/influence grid, each grouping stakeholders by level of authority, concern about outcomes, ability to influence outcomes, or ability to cause changes to planning or execution. These models are useful for small projects or projects with simple relationships. The guide adds the stakeholder cube, a refinement of the grid models combining their elements into a three-dimensional model.

The salience model and directions of influence

The salience model describes classes of stakeholders based on assessments of power — level of authority or ability to influence outcomes — urgency — need for immediate attention, either time-constrained or relating to high stakes in the outcome — and legitimacy — their involvement being appropriate. An adaptation substitutes proximity for legitimacy, meaning direct involvement in project activities. The model is useful for large, complex communities of stakeholders or where there are complex networks of relationships. Directions of influence classifies stakeholders by their influence on the work or the team: upward (senior management, sponsor, steering committee), downward (the team or specialists contributing temporarily), outward (suppliers, government departments, the public, end users, regulators), and sideward (peers of the project manager competing for scarce resources or collaborating).

The stakeholder engagement assessment matrix

A matrix that compares current and desired stakeholder engagement levels. Engagement is classified into five: unaware — unaware of the project and its potential impacts; resistant — aware of the project and potential impacts but resistant to any changes that may occur, and unsupportive of the work or outcomes; neutral — aware but neither supportive nor unsupportive; supportive — aware and supportive of the work and its outcomes; and leading — aware and actively engaged in ensuring that the project is a success. C marks the current level and D the level the team assessed as essential. The gap between current and desired for each stakeholder directs the level of communications necessary, and closing that gap is an essential element of monitoring engagement.

The five conflict resolution techniques

The guide names five general techniques, each with its place and use. Withdraw/avoid — retreating from an actual or potential conflict situation, postponing the issue to be better prepared or resolved by others. Smooth/accommodate — emphasizing areas of agreement rather than difference, conceding one's position to the needs of others to maintain harmony and relationships. Compromise/reconcile — searching for solutions bringing some satisfaction to all parties, resolving the conflict temporarily or partially, and occasionally resulting in a lose-lose situation. Force/direct — pushing one's viewpoint at the expense of others, offering only win-lose solutions, usually enforced through a power position to resolve an emergency. Collaborate/problem-solve — incorporating multiple viewpoints and insights, requiring a cooperative attitude and open dialogue that typically leads to consensus and commitment, and which can result in a win-win situation.

Engagement levelStateStance toward the work and outcomes
UnawareUnaware of the project and its impacts
ResistantAware, and resistant to resulting changesUnsupportive
NeutralAware of the projectNeither supportive nor unsupportive
SupportiveAware of the project and its impactsSupportive
LeadingAware of the project and its impactsActively engaged in ensuring success

On the Exam

The 2026 ECO gives stakeholders three consecutive tasks in Domain I, People — the heaviest domain at 33%. Task 4, engage stakeholders: identify and analyze stakeholders; analyze and tailor communication to their needs; execute the engagement plan; optimize alignment among needs, expectations, and objectives; and build trust and influence. Task 5, align stakeholder expectations: categorize stakeholders; identify stakeholder expectations; facilitate discussions to align expectations; and organize and act on mentoring opportunities. Task 6, manage stakeholder expectations: identify internal and external customer expectations; align and maintain outcomes to them; and monitor satisfaction, responding as needed. Task 8, plan and manage communication, joins them: define a communication strategy; promote transparency and collaboration; establish a feedback loop; understand reporting requirements; create reports aligned with sponsor and stakeholder expectations; and support reporting and governance processes.

The dominant pattern is a scenario describing a stakeholder objecting or disengaging, and asking what to do. Four keys settle most of it:

  • A resistant stakeholder → aware and resisting the resulting change; the remedy addresses the source of resistance rather than adding information.
  • An unaware stakeholder → does not know at all; the remedy is informing rather than persuading.
  • A question about directing communication effort → the gap between current and desired levels.
  • A new stakeholder appearing late → identification is a periodic activity reviewed at phase transitions.

What deceives is options presenting compromise as the ideal middle, while the guide warns it occasionally results in a lose-lose situation and resolves conflict temporarily or partially. So does an option treating every stakeholder with the same dose, or jumping to force in a non-emergency — the guide confines force to resolving an emergency through a power position.

Detailed Mistakes

Confusing "unaware" with "resistant"

The definitional difference is decisive: unaware means unaware of the project and its potential impacts, while resistant means aware of both but resistant to any changes that may occur. The first lacks information; the second holds an objection. Treating a resistant stakeholder with more messages multiplies what irritates them, reminding them of a change they do not want instead of addressing why they refuse it.

Choosing a classification model without regard to project size

The guide draws the line explicitly: grid models are useful for small projects or projects with simple relationships between stakeholders and the project, or within the stakeholder community itself. The salience model is useful for large, complex communities or where there are complex networks of relationships. Applying a power/interest grid to a project with hundreds of interlinked stakeholders yields a flat classification that directs no effort.

Treating compromise as always the best technique

The guide says of each technique that it has its place and use, describes compromise as resolving conflict temporarily or partially and occasionally resulting in a lose-lose situation, and describes collaborate/problem-solve as one that can result in a win-win situation. Compromise is not the golden middle but a partial solution with a cost, and reaching for it in a conflict that could be settled durably buys temporary quiet at the price of both parties' satisfaction.

Where It Does Not Apply

Classification and engagement tools presume stakeholders who can be identified and assessed for power and interest. Where they number in the millions — a possibility the guide states outright — individual handling is impossible, and the work shifts to representing categories rather than persons. A second limit applies to conflict techniques: when disruptive conflict continues, formal procedures may be used, including disciplinary actions, so the five techniques operate before that point rather than after it. A third touches classification itself: the influence, power, or interests of stakeholders may change as the project unfolds, so today's classification is not next quarter's. The error is not choosing a model but treating its output as a fixed fact — the matrix itself was built to be measured periodically rather than filled once.

Frequently asked questions

How do I classify stakeholders?

By their power and interest, using a tool like the power-interest matrix, to set the engagement style.

Which stakeholders do I manage closely?

Those highest in power and interest; they need close engagement and follow-up.

What are the elements of a communication plan?

What to communicate, to whom, when, through which channel, and how to receive feedback.

What is the best conflict resolution style?

Collaborating and problem-solving is usually best for a durable solution, compromise is a quick middle ground, and forcing is the last resort.

Should I avoid conflict?

No; conflict managed openly improves decisions, while avoiding it only defers the problem.

What is the stakeholder engagement assessment matrix?

A tool comparing each stakeholder's current engagement level with the desired one across five levels: unaware, resistant, neutral, supportive, and leading.